Photo of Malcolm TurnbullMalcolm Turnbull (Wentworth, Liberal Party, Minister for Communications) Share this | Hansard source

I thank the honourable member for his question. The overall progress of the NBN rollout in Denison is that the fixed line network is now ready for service in areas covering 11,842 premises. It is under construction in areas covering 21,200 premises; and, looking to the 18-month rollout plan, which will begin in the next year, that will include areas covering 27,800 premises. That last part will be mostly fibre-to-the-node. That means that, by June next year, work on the NBN's fixed line network will be complete in areas covering 60,800 premises in the honourable member's electorate. Virtually no other electorate in Australia will be as advanced as Denison in terms of the NBN rollout. It is impractical to outline each suburb and its upgrade timetable, but I will give the honourable member details of that later in writing.

Moving to the complaints about the NBN rollout, I will break them into four categories: firstly, the hold on the rollout due to the mismanagement of how asbestos material was removed from old infrastructure; secondly, the halt of the construction due to a commercial dispute—

Comments

No comments